Before a piece of equipment is used in production, which types of acceptance testing are typically conducted? (Choose two) Response:
The correct answer is A. Factory Acceptance Testing (FAT) B. Site Acceptance Testing (SAT). You've hit your session limit · resets 5:20pm (America/New_York)
Question
Before a piece of equipment is used in production, which types of acceptance testing are typically conducted? (Choose two) Response:
Options
- AFactory Acceptance Testing (FAT)
- BSite Acceptance Testing (SAT)
- CPersonal Acceptance Testing (PAT)
- DOnline Acceptance Testing (OAT)
How the community answered
(23 responses)- A74% (17)
- C17% (4)
- D9% (2)
Explanation