CPGP · Question #211

Which of the following is NOT a reason to initiate a "stop shipment" for quality holds? Response:

The correct answer is A. A surplus of inventory. See the full explanation below for the reasoning.

Question

Which of the following is NOT a reason to initiate a "stop shipment" for quality holds? Response:

Options

  • AA surplus of inventory
  • BIdentification of quality issues
  • CDocumentation discrepancies
  • DReceipt of damaged materials

How the community answered

(57 responses)
  • A
    79% (45)
  • B
    4% (2)
  • C
    11% (6)
  • D
    7% (4)