ASQ
CPGP · Question #11
An effective post-change analysis should: (Choose two) Response:
The correct answer is A. Confirm alignment with initial objectives B. Identify and evaluate any new risks or issues. See the full explanation below for the reasoning.
Question
An effective post-change analysis should:
(Choose two) Response:
Options
- AConfirm alignment with initial objectives
- BIdentify and evaluate any new risks or issues
- CPropose additional changes indiscriminately
- DValidate the change with external benchmarks
How the community answered
(33 responses)- A73% (24)
- C12% (4)
- D15% (5)
Community Discussion
No community discussion yet for this question.