The enterprise goal titled "Optimization of Business Process Costs" is aligned to which balanced scorecard (BSC) dimension?

The correct answer is C. Internal. https://community.mis.temple.edu/mis5203sec001sp2019/files/2019/01/COBIT-2019-Framework- Introduction-and-Methodology_res_eng_1118.pdf (24)

Governance and Management Objectives

Question

The enterprise goal titled "Optimization of Business Process Costs" is aligned to which balanced scorecard (BSC) dimension?

Options

  • AGrowth
  • BCustomer
  • CInternal

How the community answered

(41 responses)
  • A
    5% (2)
  • B
    10% (4)
  • C
    85% (35)

Explanation

https://community.mis.temple.edu/mis5203sec001sp2019/files/2019/01/COBIT-2019-Framework- Introduction-and-Methodology_res_eng_1118.pdf (24)

Topics

#enterprise goals#balanced scorecard#business process costs#internal dimension