CLSSGB · Question #79
To create standardization of financial benefit calculations project savings are typically based on savings over what period of time?
The correct answer is B. 12 months. You've hit your limit · resets 12:50am (America/New_York)
Define Phase
Question
To create standardization of financial benefit calculations project savings are typically based on savings over what period of time?
Options
- A6 months
- B12 months
- C24 months
- DThe remainder of the calendar year
- EThe remainder of the fiscal year
How the community answered
(33 responses)- A3% (1)
- B91% (30)
- E6% (2)
Explanation
You've hit your limit · resets 12:50am (America/New_York)
Topics
#financial benefits#project savings#standardization