Training cost is $4,000 and a project required an initial investment of $30,000. If the project yields monthly savings of $2,000 beginning after 3 months, what is the payback period in months…
The correct answer is B. 20. You've hit your limit · resets 12:50am (America/New_York)
Define Phase
Question
Training cost is $4,000 and a project required an initial investment of $30,000. If the project yields monthly savings of $2,000 beginning after 3 months, what is the payback period in months (before money costs and taxes)?
Options
- A10
- B20
- C27
- D33
How the community answered
(34 responses)- A3% (1)
- B71% (24)
- C18% (6)
- D9% (3)