nerdexam
GAQM

CLSSBB · Question #2

For her injection molding project a Belt needed to track the percentage of defectives of a particular sample set so she used a ____________ to display the data?

The correct answer is D. P Chart. You've hit your limit · resets 12:50am (America/New_York)

Control Phase

Question

For her injection molding project a Belt needed to track the percentage of defectives of a particular sample set so she used a ____________ to display the data?

Options

  • AIndividual Chart
  • BC Chart
  • CXbar Chart
  • DP Chart

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    3% (1)
  • D
    93% (28)

Explanation

You've hit your limit · resets 12:50am (America/New_York)

Topics

#P Chart#attribute data#defectives#SPC

Community Discussion

No community discussion yet for this question.

Full CLSSBB Practice