For her injection molding project a Belt needed to track the percentage of defectives of a particular sample set so she used a ______ to display the data?

The correct answer is D. P Chart. You've hit your limit · resets 12:50am (America/New_York)

Control Phase

Question

For her injection molding project a Belt needed to track the percentage of defectives of a particular sample set so she used a ______ to display the data?

Options

  • AIndividual Chart
  • BC Chart
  • CXbar Chart
  • DP Chart

How the community answered

(41 responses)
  • B
    5% (2)
  • C
    7% (3)
  • D
    88% (36)

Explanation

You've hit your limit · resets 12:50am (America/New_York)

Topics

#P chart#attribute control charts#percentage defective#SPC