CLSSBB · Question #13

Upon completion and validation of an improvement to a process a Belt and the Project Team create a Control Plan that contains which of these?

The correct answer is D. All of the above. You've hit your limit · resets 12:50am (America/New_York)

Control Phase

Question

Upon completion and validation of an improvement to a process a Belt and the Project Team create a Control Plan that contains which of these?

Options

  • AStandard operating work description of the process change
  • BDescription of the monitoring system in place to assure continued compliance
  • CSummary of the targeted critical metrics for process performance measurement
  • DAll of the above

How the community answered

(32 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    3% (1)
  • D
    88% (28)

Explanation

You've hit your limit · resets 12:50am (America/New_York)

Topics

#control plan#process monitoring#process performance#SPC