When an organization experiences a disruptive event, the business continuity plan (BCP) should be triggered PRIMARILY based on:

The correct answer is A. expected duration of outage. The primary trigger for a Business Continuity Plan (BCP) is the anticipated duration of a disruption, as it directly impacts the organization's ability to maintain critical operations.

Submitted by kim_seoul· Apr 18, 2026Information Security Incident Management

Question

When an organization experiences a disruptive event, the business continuity plan (BCP) should be triggered PRIMARILY based on:

Options

  • Aexpected duration of outage.
  • Bthe root cause of the event.
  • Ctype of security incident.
  • Dmanagement direction.

How the community answered

(36 responses)
  • A
    94% (34)
  • B
    3% (1)
  • C
    3% (1)

Why each option

The primary trigger for a Business Continuity Plan (BCP) is the anticipated duration of a disruption, as it directly impacts the organization's ability to maintain critical operations.

Aexpected duration of outage.Correct

The expected duration of an outage is the primary trigger for a BCP because the plan's purpose is to ensure the continuity of critical business functions when normal operations are interrupted for a significant period. If the outage is short and can be resolved within standard operational recovery times, a full BCP activation might not be necessary, but a longer anticipated duration necessitates immediate BCP invocation to mitigate prolonged business impact.

Bthe root cause of the event.

While understanding the root cause is crucial for remediation, it is not the primary factor for *triggering* BCP, which focuses on impact, not cause.

Ctype of security incident.

The type of security incident informs incident response, but the BCP trigger focuses on the *business impact* and *duration* of the disruption, not just the incident type.

Dmanagement direction.

Management direction is essential for BCP oversight and approval, but the *trigger* itself is an objective measure of disruption severity, often predefined in RTOs (Recovery Time Objectives).

Concept tested: Business Continuity Plan (BCP) triggers

Source: https://learn.microsoft.com/en-us/azure/architecture/resiliency/recovery-objectives