CISA · Question #324
Which of the following is MOST important to have in place to manage the risk of a resource shortage when there are multiple IT investment projects in progress?
The correct answer is C. IT portfolio management. IT portfolio management is the most important to manage the risk of resource shortages when multiple IT investment projects are in progress. It helps ensure that resources are allocated efficiently across projects, prioritizing them based on strategic objectives and resource
Question
Which of the following is MOST important to have in place to manage the risk of a resource shortage when there are multiple IT investment projects in progress?
Options
- AIT project management
- BIT risk management
- CIT portfolio management
- DIT change management
How the community answered
(45 responses)- A2% (1)
- B11% (5)
- C80% (36)
- D7% (3)
Explanation
IT portfolio management is the most important to manage the risk of resource shortages when multiple IT investment projects are in progress. It helps ensure that resources are allocated efficiently across projects, prioritizing them based on strategic objectives and resource