Which of the following should be used as the PRIMARY basis for prioritizing IT projects and initiatives?
The correct answer is B. Expected business value. IT exists to enable and support business objectives, so projects should be prioritized by the value they deliver to the organization. Cost, risk, and resources are important secondary factors used to refine prioritization, but they cannot serve as the primary basis - a low-cost p
Question
Which of the following should be used as the PRIMARY basis for prioritizing IT projects and initiatives?
Options
- AEstimated cost and time
- BExpected business value
- CLevel of risk reduction
- DAvailable resources
How the community answered
(25 responses)- A8% (2)
- B88% (22)
- D4% (1)
Explanation
IT exists to enable and support business objectives, so projects should be prioritized by the value they deliver to the organization. Cost, risk, and resources are important secondary factors used to refine prioritization, but they cannot serve as the primary basis - a low-cost project with no business value should not rank above a high-value project simply because it is cheap. Business value anchors the decision in strategy, ensuring IT investments produce meaningful outcomes aligned with organizational goals.