CISA · Question #148
An IS auditor has been asked to review the integrity of data transfer between two business-critical systems that have not been tested since implementation. Which of the following would provide the MOS
The correct answer is D. Previous system interface testing records. Previous system interface testing records are the most valuable starting point for planning an audit of systems not tested since implementation. These records document the original scope of testing, known deficiencies, accepted risks, and baseline behavior expectations at the tim
Question
An IS auditor has been asked to review the integrity of data transfer between two business-critical systems that have not been tested since implementation. Which of the following would provide the MOST useful information to plan an audit?
Options
- AQuality assurance (QA) testing
- BSystem change logs
- CIT testing policies and procedures
- DPrevious system interface testing records
How the community answered
(71 responses)- A6% (4)
- B13% (9)
- C4% (3)
- D77% (55)
Explanation
Previous system interface testing records are the most valuable starting point for planning an audit of systems not tested since implementation. These records document the original scope of testing, known deficiencies, accepted risks, and baseline behavior expectations at the time of go-live. They allow the auditor to identify what was tested, what was not, and where risk may have accumulated over time. QA testing (A) is a forward-looking activity, not a planning input. Change logs (B) show modifications but not the original interface testing baseline. IT testing policies (C) describe how testing should be done but do not provide system-specific evidence.