CHANGE-MANAGEMENT-FOUNDATION · Question #54

Which of the following is a purpose of creating a change management plan when preparing for change?

The correct answer is D. Record a list of all the change risks and the responsive actions required. One of the purposes of creating a change management plan when preparing for change is to record a list of all the change risks and the responsive actions required. This helps to identify potential threats and opportunities for the change and plan how to mitigate or exploit…

Planning and Implementing Change

Question

Which of the following is a purpose of creating a change management plan when preparing for change?

Options

  • ADocument the set of typically recurring actions that contribute to change readness'
  • BProvide a detailed schedule of project and their dependencies
  • CCapture of full list of issues to be resolved before change can start
  • DRecord a list of all the change risks and the responsive actions required.

How the community answered

(25 responses)
  • A
    8% (2)
  • B
    4% (1)
  • D
    88% (22)

Explanation

One of the purposes of creating a change management plan when preparing for change is to record a list of all the change risks and the responsive actions required. This helps to identify potential threats and opportunities for the change and plan how to mitigate or exploit them. The other options are not purposes of a change management plan, but rather outcomes or inputs of other processes or activities.

Topics

#change management plan#change risks#planning#risk response