CGEIT · Question #684

A CIO engages a consulting firm to conduct a benchmark analysis of the organization's IT governance framework against industry best practices. Several recommendations to improve the maturity of the…

The correct answer is A. Evaluate the feasibility of the recommendations. After receiving recommendations to improve IT governance, the CIO's next immediate action should be to evaluate the feasibility of these recommendations. This step assesses their practicality, resource implications, and alignment with organizational goals before proceeding with…

Submitted by rohit_dlh· Apr 18, 2026Governance of Enterprise IT

Question

A CIO engages a consulting firm to conduct a benchmark analysis of the organization's IT governance framework against industry best practices. Several recommendations to improve the maturity of the framework are identified. Which of the following should be the CIO's NEXT course of action?

Options

  • AEvaluate the feasibility of the recommendations.
  • BObtain approval from the IT steering committee to implement the recommendations.
  • CDevelop a plan to integrate the recommendations.
  • DAppoint a project manager to implement the recommendations.

How the community answered

(19 responses)
  • A
    79% (15)
  • B
    5% (1)
  • C
    11% (2)
  • D
    5% (1)

Why each option

After receiving recommendations to improve IT governance, the CIO's next immediate action should be to evaluate the feasibility of these recommendations. This step assesses their practicality, resource implications, and alignment with organizational goals before proceeding with planning or approval.

AEvaluate the feasibility of the recommendations.Correct

After receiving recommendations for improving IT governance maturity, the CIO's next crucial step is to evaluate the feasibility of these recommendations. This involves assessing their practicality, resource requirements (budget, staff, technology), potential impact, and alignment with the organization's strategic objectives before seeking approvals or developing implementation plans.

BObtain approval from the IT steering committee to implement the recommendations.

Seeking approval from the IT steering committee is premature before the CIO has assessed the feasibility and understood the implications of the recommendations.

CDevelop a plan to integrate the recommendations.

Developing a plan to integrate the recommendations would be done *after* their feasibility has been evaluated and they have been deemed suitable for implementation.

DAppoint a project manager to implement the recommendations.

Appointing a project manager for implementation is a step taken much later, once the recommendations have been deemed feasible, approved, and a detailed implementation plan is in place.

Concept tested: IT governance improvement process

Source: https://learn.microsoft.com/en-us/azure/cloud-adoption-framework/govern/considerations/

Topics

#IT governance#benchmarking#feasibility analysis#recommendation management