An IT strategy committee wants to ensure stakeholders understand who owns each strategic objective. To enable this understanding, which of the following should be communicated to stakeholders?
The correct answer is A. A RACI chart. To clearly communicate ownership of strategic objectives to stakeholders, an IT strategy committee should provide a RACI chart.
Question
An IT strategy committee wants to ensure stakeholders understand who owns each strategic objective. To enable this understanding, which of the following should be communicated to stakeholders?
Options
- AA RACI chart
- BThe strategic plan
- CPerformance measure
- DRisk owners
How the community answered
(19 responses)- A89% (17)
- C5% (1)
- D5% (1)
Why each option
To clearly communicate ownership of strategic objectives to stakeholders, an IT strategy committee should provide a RACI chart.
A RACI (Responsible, Accountable, Consulted, Informed) chart explicitly defines who is accountable (the owner) for each specific strategic objective or task. By communicating a RACI chart, the IT strategy committee ensures that all stakeholders clearly understand the designated owner for each objective, promoting clarity, accountability, and efficient execution. This removes ambiguity regarding who is ultimately answerable for the success or failure of an objective.
The strategic plan outlines the objectives themselves, but it typically doesn't detail individual ownership for each objective.
Performance measures track progress but do not define who owns the objective itself.
Risk owners are responsible for managing specific risks, not necessarily the overall strategic objectives.
Concept tested: Role and responsibility assignment (RACI)