IsacaIsaca
CGEIT · Question #43
CGEIT Question #43: Real Exam Question with Answer & Explanation
The correct answer is C: Implementing a review and approval process for each phase. To best improve an enterprise's ability to manage large IT investment projects, implementing a review and approval process for each project phase is crucial.
Submitted by yasin.bd· Apr 18, 2026Governance of Enterprise IT
Question
Which of the following would BEST help to improve an enterprise's ability to manage large IT investment projects?
Options
- ACreating a change management board
- BReviewing and evaluating existing business cases
- CImplementing a review and approval process for each phase
- DPublishing the IT approval process online for wider scrutiny
Explanation
To best improve an enterprise's ability to manage large IT investment projects, implementing a review and approval process for each project phase is crucial.
Common mistakes.
- A. Creating a change management board is primarily for handling project changes, not for the overall management of large IT investment projects across all phases.
- B. Reviewing existing business cases helps in selecting future projects, but does not directly improve the management of current large IT investment projects.
- D. Publishing the IT approval process online increases transparency but does not, by itself, enhance the enterprise's ability to actively manage projects through their lifecycle.
Concept tested. Project lifecycle governance and control
Topics
#Project Governance#IT Investment Management#Phase-gate Review#Project Control
Community Discussion
No community discussion yet for this question.