Which of the following is the prime purpose of the Manage Stakeholders Expectations process?
The correct answer is C. Resolve issues. The prime purpose of the Manage Stakeholders Expectations process is to resolve issues that may arise from the different needs, expectations, and perspectives of the stakeholders. The Manage Stakeholders Expectations process involves communicating with the stakeholders, addressin
Question
Which of the following is the prime purpose of the Manage Stakeholders Expectations process?
Options
- AIdentify stakeholders
- BClose project
- CResolve issues
- DUpdating risk registers
How the community answered
(31 responses)- B3% (1)
- C94% (29)
- D3% (1)
Explanation
The prime purpose of the Manage Stakeholders Expectations process is to resolve issues that may arise from the different needs, expectations, and perspectives of the stakeholders. The Manage Stakeholders Expectations process involves communicating with the stakeholders, addressing their concerns, managing their conflicts, and obtaining their feedback and approval. The Manage Stakeholders Expectations process helps to ensure the satisfaction and support of the stakeholders throughout the project lifecycle. The other options are not the prime purpose of the Manage Stakeholders Expectations process, but the purpose of other processes. The Identify Stakeholders process is the process of identifying the people, groups, or organizations that have an interest or influence on the project or the solution. The Close Project process is the process of finalizing all the activities and deliverables of the project and formally completing the project. The Updating Risk Registers process is the process of updating the document that records the identified risks, their analysis, and their response plans.