CCBA · Question #647
Vijay has noticed that the non-availability of resources is affecting the timing of the business analysis activities. He is trying to prevent the occurrence of the other factors which may affect the t
The correct answer is D. All of the aboveright. The timing of business analysis activities can also be affected by: 1. the availability of resources, 2. priority and/or urgency of the initiative, 3. other concurrent initiatives, or 4. constraints such as contract terms or regulatory deadlines. Choice A is one of the factors Vi
Question
Vijay has noticed that the non-availability of resources is affecting the timing of the business analysis activities. He is trying to prevent the occurrence of the other factors which may affect the timing of the business analysis activities. For which of the factors he needs to come up with the mitigation plan?
Options
- AConstraints such as contract terms or regulatory deadlines
- BPriority and / or urgency of the initiative
- COther concurrent initiatives
- DAll of the aboveright
How the community answered
(53 responses)- A2% (1)
- B8% (4)
- C4% (2)
- D87% (46)
Explanation
The timing of business analysis activities can also be affected by: 1. the availability of resources, 2. priority and/or urgency of the initiative, 3. other concurrent initiatives, or 4. constraints such as contract terms or regulatory deadlines. Choice A is one of the factors Vijay needs to focus to come up with the mitigation plan. Choice B is another factor Vijay needs to focus to come up with the mitigation plan. Choice C is another factor Vijay needs to focus to come up with the mitigation plan. Choice D is correct, since all the choices A, B and C are the valid factors Vijay needs to focus to come up with the mitigation plan.
Topics
Community Discussion
No community discussion yet for this question.