The business analyst is focusing on minimizing upfront uncertainty and ensuring that the solution is defined before implementation begins in order to maximize control and minimize risk. This…

The correct answer is D. None of the aboveright. Choice A is not correct, since the given situation is a valid situation for using the predictive Choice B is not correct, since the given situation is a valid situation for using the predictive Choice C is not correct, since the given situation is a valid situation for using…

Business Analysis Planning and Monitoring

Question

The business analyst is focusing on minimizing upfront uncertainty and ensuring that the solution is defined before implementation begins in order to maximize control and minimize risk. This predictive approach is mostly not used by the business analyst during which of the following situations?

Options

  • AWhere the requirements can effectively be defined ahead of implementation
  • BThe risk of an incorrect implementation is unacceptably high
  • CWhen engaging stakeholders presents significant challenges
  • DNone of the aboveright

How the community answered

(45 responses)
  • A
    7% (3)
  • B
    16% (7)
  • C
    2% (1)
  • D
    76% (34)

Explanation

Choice A is not correct, since the given situation is a valid situation for using the predictive Choice B is not correct, since the given situation is a valid situation for using the predictive Choice C is not correct, since the given situation is a valid situation for using the predictive Choice D is correct, since all the choices A, B and C are the valid situation for using the predictive

Topics

#predictive approach#adaptive approach#BA methodology#risk minimization

Community Discussion

No community discussion yet for this question.