The business analyst (BA) has an item logged in the action items register requiring the verification of forthcoming legislation in the next 3 months that might have an impact on the proposed architect
The correct answer is C. Assess the impact immediately. The BA should assess the impact of the forthcoming legislation immediately when it is logged in the action items register. This is because assessing the impact of a change is a technique that involves analyzing how a change affects the existing or proposed solution, business proc
Question
The business analyst (BA) has an item logged in the action items register requiring the verification of forthcoming legislation in the next 3 months that might have an impact on the proposed architecture. What should the BA do next?
Options
- ATransfer the item to the legal department
- BDetermine the performance measures
- CAssess the impact immediately
- DPresent the item to the project manager
How the community answered
(31 responses)- A3% (1)
- B13% (4)
- C74% (23)
- D10% (3)
Explanation
The BA should assess the impact of the forthcoming legislation immediately when it is logged in the action items register. This is because assessing the impact of a change is a technique that involves analyzing how a change affects the existing or proposed solution, business processes, stakeholders, or organization. Assessing the impact of the forthcoming legislation immediately can help the BA to identify and mitigate any potential risks or issues that might have an impact on the proposed architecture and plan accordingly. The other options are not as urgent or appropriate as assessing the impact immediately.