CCBA · Question #364
The business analyst (BA) recommended a new application be rolled out in phases. After reviewing alternatives, the project sponsor agreed. What does the BA expect to achieve by this approach?
The correct answer is C. Maximize benefits. The scenario describes a task that involves recommending a phased rollout of a new application. The phased rollout is a technique used by business analysts to deliver the solution incrementally, in stages or iterations, rather than all at once. The BA expects to achieve several…
Question
The business analyst (BA) recommended a new application be rolled out in phases. After reviewing alternatives, the project sponsor agreed. What does the BA expect to achieve by this approach?
Options
- AIncrease stakeholder engagement
- BMaximize allocation
- CMaximize benefits
- DIncrease process validation
How the community answered
(28 responses)- A4% (1)
- B7% (2)
- C86% (24)
- D4% (1)
Explanation
The scenario describes a task that involves recommending a phased rollout of a new application. The phased rollout is a technique used by business analysts to deliver the solution incrementally, in stages or iterations, rather than all at once. The BA expects to achieve several benefits by this approach, such as: Reducing the risk and complexity of the project by breaking it down into smaller and manageable Increasing the quality and usability of the solution by incorporating feedback and testing at each Enhancing the value and satisfaction of the stakeholders by delivering the most important or urgent features first Improving the alignment and adaptation of the solution to the changing business needs and