Before beginning requirements elicitation, a business analyst (BA) has planned the necessary activities, identified needed stakeholders, and documented this in the Business Analysis Plan. Which…

The correct answer is C. Conduct a review of the plan with the stakeholders and adjust according to the feedback received. The scenario describes a task that involves planning the requirements elicitation activities and identifying the needed stakeholders. The task requires the BA to ensure that the stakeholders are available when required for the elicitation process. The best approach to achieve…

Business Analysis Planning and Monitoring

Question

Before beginning requirements elicitation, a business analyst (BA) has planned the necessary activities, identified needed stakeholders, and documented this in the Business Analysis Plan. Which approach will help the BA ensure that stakeholders are available when required?

Options

  • ATalk to the stakeholders' managers to ensure the resources will be available
  • BSend meeting invitations well in advance so stakeholders can plan in time
  • CConduct a review of the plan with the stakeholders and adjust according to the feedback received
  • DRequest an introduction letter from the business sponsor highlighting the importance of the

How the community answered

(51 responses)
  • A
    4% (2)
  • C
    94% (48)
  • D
    2% (1)

Explanation

The scenario describes a task that involves planning the requirements elicitation activities and identifying the needed stakeholders. The task requires the BA to ensure that the stakeholders are available when required for the elicitation process. The best approach to achieve this is to conduct a review of the plan with the stakeholders and adjust according to the feedback received. This would help to establish a mutual understanding and agreement on the elicitation objectives, scope, schedule, and methods. It would also allow the BA to address any concerns or issues that the stakeholders may have regarding their availability and involvement.

Topics

#stakeholder availability#elicitation planning#plan review#stakeholder feedback