Several risks were identified for an upcoming change initiative. One risk is related to a slippage concern because of loose gravel at the local site of the change initiative. The business analyst (BA)

The correct answer is B. Mitigate. Requiring slip-resistant boots reduces the likelihood of harm from the identified risk, which is the definition of risk mitigation.

Business Analysis Planning and Monitoring

Question

Several risks were identified for an upcoming change initiative. One risk is related to a slippage concern because of loose gravel at the local site of the change initiative. The business analyst (BA) has recommended that all on-site stakeholders must wear durable, slip-resistant boots while the change initiative is being executed. This is an example of which type of risk treatment?

Options

  • ATransfer
  • BMitigate
  • CAccept
  • DAvoid

How the community answered

(61 responses)
  • A
    7% (4)
  • B
    70% (43)
  • C
    3% (2)
  • D
    20% (12)

Why each option

Requiring slip-resistant boots reduces the likelihood of harm from the identified risk, which is the definition of risk mitigation.

ATransfer

Transfer shifts the financial or legal responsibility for a risk to a third party, such as through an insurance policy or a contract indemnity clause.

BMitigateCorrect

Risk mitigation involves taking proactive steps to reduce the probability or impact of a risk event occurring. Requiring durable, slip-resistant boots directly reduces the likelihood that stakeholders will be harmed by loose gravel, thereby diminishing both the probability and potential impact of this identified risk without eliminating the activity entirely.

CAccept

Accept means acknowledging the risk and choosing not to take action, typically because the cost of treatment outweighs the expected impact of the risk.

DAvoid

Avoid would mean eliminating the risk entirely by changing the plan - for example, relocating the change initiative away from the site with loose gravel.

Concept tested: Risk treatment strategy - mitigation vs other responses

Topics

#risk treatment#risk mitigation#risk management#on-site risk

Community Discussion