The correct answer is A. Process configuration. A process configuration is a flowchart that maps all project processes and the interfaces between them, giving stakeholders a visual overview of how processes connect.

Question

Which of the following is a flowchart that shows all the processes and the interfaces that interact with the project processes?

Options

  • AProcess configuration
  • BPareto chart
  • CControl chart
  • DQuality baseline
  • ERACI chart

Explanation

A process configuration is a flowchart that maps all project processes and the interfaces between them, giving stakeholders a visual overview of how processes connect.

Common mistakes.

  • B. A Pareto chart is a bar graph used in quality management to rank defect causes by frequency, applying the 80/20 rule - it does not map process flows or interfaces.
  • C. A control chart is a statistical quality tool used to monitor process performance over time against control limits - it tracks data trends, not process relationships or interfaces.
  • D. A quality baseline documents the agreed-upon quality standards and metrics for a project - it is a reference document, not a flowchart of process interactions.
  • E. A RACI chart assigns roles and responsibilities (Responsible, Accountable, Consulted, Informed) to project tasks - it maps people to activities, not processes to interfaces.

Concept tested. Process configuration flowchart in project management