CBAP · Question #201
CBAP Question #201: Real Exam Question with Answer & Explanation
The correct answer is A. Process configuration. A process configuration is a flowchart that maps all project processes and the interfaces between them, giving stakeholders a visual overview of how processes connect.
Question
Which of the following is a flowchart that shows all the processes and the interfaces that interact with the project processes?
Options
- AProcess configuration
- BPareto chart
- CControl chart
- DQuality baseline
- ERACI chart
Explanation
A process configuration is a flowchart that maps all project processes and the interfaces between them, giving stakeholders a visual overview of how processes connect.
Common mistakes.
- B. A Pareto chart is a bar graph used in quality management to rank defect causes by frequency, applying the 80/20 rule - it does not map process flows or interfaces.
- C. A control chart is a statistical quality tool used to monitor process performance over time against control limits - it tracks data trends, not process relationships or interfaces.
- D. A quality baseline documents the agreed-upon quality standards and metrics for a project - it is a reference document, not a flowchart of process interactions.
- E. A RACI chart assigns roles and responsibilities (Responsible, Accountable, Consulted, Informed) to project tasks - it maps people to activities, not processes to interfaces.
Concept tested. Process configuration flowchart in project management
Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok