CBAP · Question #191

Which of the following techniques is used to divide a project into controllable parts?

The correct answer is C. WBS. Work Breakdown Structure (WBS) is the project management technique used to decompose a project into smaller, more manageable components.

Business Analysis Planning and Monitoring

Question

Which of the following techniques is used to divide a project into controllable parts?

Options

  • AGantt Chart
  • BPareto Chart
  • CWBS
  • DCPM

How the community answered

(63 responses)
  • A
    2% (1)
  • B
    10% (6)
  • C
    84% (53)
  • D
    5% (3)

Why each option

Work Breakdown Structure (WBS) is the project management technique used to decompose a project into smaller, more manageable components.

AGantt Chart

A Gantt Chart is a scheduling tool that displays tasks over time but does not itself divide the project scope into structured components.

BPareto Chart

A Pareto Chart is a quality tool that ranks defects or issues by frequency, not a technique for decomposing project scope.

CWBSCorrect

A WBS hierarchically decomposes the total scope of a project into smaller, controllable work packages that can be scheduled, cost-estimated, and assigned. It is defined in PMBOK as the foundational tool for scope management and project decomposition.

DCPM

Critical Path Method (CPM) is a scheduling technique used to identify the longest sequence of dependent tasks, not to break down project scope.

Concept tested: Work Breakdown Structure for project scope decomposition

Source: https://www.pmi.org/learning/library/applying-work-breakdown-structure-project-lifecycle-6979

Topics

#WBS#work breakdown structure#project decomposition#scope management