IIBA
CBAP · Question #1
CBAP Question #1: Real Exam Question with Answer & Explanation
The correct answer is C. You may need to determine which requirements are most critical so the analysis and. Prioritizing requirements helps the team focus its limited time and resources on the most critical items first, ensuring high-value work is completed even if lower-priority items are deferred.
Question
One of the processes within requirements analysis is to prioritize requirements. As a business analyst why would you ever want to prioritize requirements?
Options
- AYou may need to determine the cost of each requirement.
- BYou may need to determine the schedule for each requirement.
- CYou may need to determine which requirements are most critical so the analysis and
- DYou may need to determine which requirements are most critical so additional risk analysis
Explanation
Prioritizing requirements helps the team focus its limited time and resources on the most critical items first, ensuring high-value work is completed even if lower-priority items are deferred.
Common mistakes.
- A. Determining cost is a separate estimation activity that may use prioritization as an input, but it is not the reason for prioritizing requirements.
- B. Scheduling is a project management activity that follows prioritization; it is a consequence of prioritization, not its purpose.
- D. Risk analysis is a distinct process; while prioritization may inform risk decisions, conducting additional risk analysis is not the primary motivation for prioritizing requirements.
Concept tested. Requirements prioritization purpose in business analysis
Reference. https://www.iiba.org/career-resources/a-business-analysis-body-of-knowledge/
Community Discussion
No community discussion yet for this question.