CAPM · Question #420
How is program success measured?
The correct answer is A. By delivering the benefit of managing the program's projects in a coordinated manner. Program success is measured by the delivery of benefits achieved through coordinated management of related projects-the whole is greater than the sum of its parts. This distinguishes programs from portfolios and from individual projects. Option B describes how individual…
Question
Options
- ABy delivering the benefit of managing the program's projects in a coordinated manner
- BBy the quality, timeliness, cost-effectiveness, and customer satisfaction of the product or service
- CBy completing the right projects to achieve objectives rather than completing projects the right way
- DBy aggregating the successes of the individual projects in the program
How the community answered
(37 responses)- A95% (35)
- C3% (1)
- D3% (1)
Explanation
Program success is measured by the delivery of benefits achieved through coordinated management of related projects-the whole is greater than the sum of its parts. This distinguishes programs from portfolios and from individual projects. Option B describes how individual project success is typically measured (quality, time, cost, satisfaction). Option C describes portfolio management (right projects). Option D (aggregating individual project successes) misses the point; a program delivers synergistic benefits that individual projects cannot achieve alone.