CAPM · Question #420
CAPM Question #420: Real Exam Question with Answer & Explanation
The correct answer is A: By delivering the benefit of managing the program's projects in a coordinated manner. See the full explanation below for the reasoning.
Project Management Fundamentals and Core Concepts
Question
How is program success measured?
Options
- ABy delivering the benefit of managing the program's projects in a coordinated manner
- BBy the quality, timeliness, cost-effectiveness, and customer satisfaction of the product or service
- CBy completing the right projects to achieve objectives rather than completing projects the right way
- DBy aggregating the successes of the individual projects in the program
Topics
#Program Management#Program Success#Benefits Realization#Project vs Program