CAPM · Question #420

How is program success measured?

The correct answer is A. By delivering the benefit of managing the program's projects in a coordinated manner. Program success is measured by the delivery of benefits achieved through coordinated management of related projects-the whole is greater than the sum of its parts. This distinguishes programs from portfolios and from individual projects. Option B describes how individual…

Project Management Fundamentals and Core Concepts

Question

How is program success measured?

Options

  • ABy delivering the benefit of managing the program's projects in a coordinated manner
  • BBy the quality, timeliness, cost-effectiveness, and customer satisfaction of the product or service
  • CBy completing the right projects to achieve objectives rather than completing projects the right way
  • DBy aggregating the successes of the individual projects in the program

How the community answered

(37 responses)
  • A
    95% (35)
  • C
    3% (1)
  • D
    3% (1)

Explanation

Program success is measured by the delivery of benefits achieved through coordinated management of related projects-the whole is greater than the sum of its parts. This distinguishes programs from portfolios and from individual projects. Option B describes how individual project success is typically measured (quality, time, cost, satisfaction). Option C describes portfolio management (right projects). Option D (aggregating individual project successes) misses the point; a program delivers synergistic benefits that individual projects cannot achieve alone.

Topics

#Program Management#Program Success#Benefits Realization#Project vs Program