CAPM · Question #419

What do top project managers do to maximize their sphere of influence within a project team?

The correct answer is D. Demonstrate superior relationship and communication skills while displaying a positive attitude. The sphere of influence is maximized through interpersonal effectiveness-strong relationship-building and communication skills combined with a positive attitude are the core traits that earn trust and respect within a team, which is the foundation of influence. Option A relates t

Project Management Fundamentals and Core Concepts

Question

What do top project managers do to maximize their sphere of influence within a project team?

Options

  • AConsider management standards, economic factors, and sustainability strategies
  • BContribute knowledge and expertise to others within the profession
  • CAddress political and strategic issues that impact the project's visibility or quality
  • DDemonstrate superior relationship and communication skills while displaying a positive attitude

How the community answered

(55 responses)
  • A
    2% (1)
  • B
    2% (1)
  • C
    2% (1)
  • D
    95% (52)

Explanation

The sphere of influence is maximized through interpersonal effectiveness-strong relationship-building and communication skills combined with a positive attitude are the core traits that earn trust and respect within a team, which is the foundation of influence. Option A relates to strategic considerations, B relates to professional contribution outside the project, and C relates to organizational politics. None of these directly maximize a PM's interpersonal influence within the project team the way D does.

Topics

#Leadership#Communication Skills#Interpersonal Skills#Influence