nerdexam
PMIPMI

CAPM · Question #4

CAPM Question #4: Real Exam Question with Answer & Explanation

The correct answer is C: Compromise/Reconcile. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties in order to temporarily or partially resolve the problem. Which technique should the project manager use?

Options

  • AWithdraw/Avoid
  • BSmooth/Accommodate
  • CCompromise/Reconcile
  • DCollaborate/Problem Solve

Topics

#Conflict Resolution#Project Team Management#Communication

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions