CAPM · Question #3

Which is the correct hierarchy in a project environment, from most to least inclusive?

The correct answer is B. Portfolios, programs, then projects. In the PMI governance hierarchy, Portfolios are the most inclusive level - they contain programs and/or independent projects aligned to strategic objectives. Programs are collections of related projects managed in a coordinated way to obtain benefits not available from managing…

Project Management Fundamentals and Core Concepts

Question

Which is the correct hierarchy in a project environment, from most to least inclusive?

Options

  • AProjects, portfolios, then programs
  • BPortfolios, programs, then projects
  • CPortfolios, projects, then programs
  • DProjects, programs, then portfolios

How the community answered

(27 responses)
  • A
    7% (2)
  • B
    89% (24)
  • D
    4% (1)

Explanation

In the PMI governance hierarchy, Portfolios are the most inclusive level - they contain programs and/or independent projects aligned to strategic objectives. Programs are collections of related projects managed in a coordinated way to obtain benefits not available from managing them individually. Projects are the least inclusive, representing a single temporary endeavor. The correct order from most to least inclusive is: Portfolios → Programs → Projects.

Topics

#Project hierarchy#Portfolios#Programs#Projects