CAPM · Question #3
Which is the correct hierarchy in a project environment, from most to least inclusive?
The correct answer is B. Portfolios, programs, then projects. In the PMI governance hierarchy, Portfolios are the most inclusive level - they contain programs and/or independent projects aligned to strategic objectives. Programs are collections of related projects managed in a coordinated way to obtain benefits not available from managing…
Question
Options
- AProjects, portfolios, then programs
- BPortfolios, programs, then projects
- CPortfolios, projects, then programs
- DProjects, programs, then portfolios
How the community answered
(27 responses)- A7% (2)
- B89% (24)
- D4% (1)
Explanation
In the PMI governance hierarchy, Portfolios are the most inclusive level - they contain programs and/or independent projects aligned to strategic objectives. Programs are collections of related projects managed in a coordinated way to obtain benefits not available from managing them individually. Projects are the least inclusive, representing a single temporary endeavor. The correct order from most to least inclusive is: Portfolios → Programs → Projects.
Topics