CAPM · Question #240

CAPM Question #240: Real Exam Question with Answer & Explanation

The correct answer is C: Professional discipline. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

A project manager is talking with their manager about the advantages of following a particular project management approach. What component of the project manager's sphere of influence does this represent?

Options

  • AThe project
  • BThe organization
  • CProfessional discipline
  • DAcross disciplines

Topics

#Project Manager Role#Sphere of Influence#Professional Discipline