Question

With regard to a project manager's sphere of influence in a project, which of the following does the project manager influence most directly?

Options

  • ASuppliers
  • BCustomers
  • CGoverning bodies
  • DProject team

Topics

#Project Manager Role#Sphere of Influence#Team Management