PMIPMI
CAPM · Question #129
CAPM Question #129: Real Exam Question with Answer & Explanation
The correct answer is C: As soon as the project charter has been approved. See the full explanation below for the reasoning.
Project Management Fundamentals and Core Concepts
Question
Stakeholder identification and engagement should begin during what phrase of the project?
Options
- AAfter the project management plan is completed
- BAfter the stakeholder engagement plan is completed
- CAs soon as the project charter has been approved
- DAfter the communications management plan is completed
Topics
#Stakeholder Management#Project Initiation#Project Charter#Project Process Groups
Community Discussion
No community discussion yet for this question.