CAPM · Question #119

CAPM Question #119: Real Exam Question with Answer & Explanation

The correct answer is D: Ability to plan and prioritize, gather the right artifacts available for each project, and focus on critical success factors. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

Which of the following are components of the technical project management skill?

Options

  • AAbility to explain business aspects of the project, business strategy, goals and objectives, and business value
  • BAbility to deal with people, to be collaborative, and to apply persuasion and negotiation
  • CAbility to focus on relationships with people, inspire trust, and implement decisions and actions that support the business strategy
  • DAbility to plan and prioritize, gather the right artifacts available for each project, and focus on critical success factors

Topics

#Technical Project Management#PMI Talent Triangle#Project Management Skills#Planning and Prioritization