CAPM · Question #118

CAPM Question #118: Real Exam Question with Answer & Explanation

The correct answer is A: Company culture. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

What can the project manager find among the factors that could lead a project to be tailored?

Options

  • ACompany culture
  • BReturn on investment
  • CEarned Value
  • DSchedule Performance Index

Topics

#Tailoring#Organizational Culture#Enterprise Environmental Factors (EEFs)