CAP · Question #394
You work as a project manager for BlueWell Inc. You are preparing to plan risk responses for your project with your team. How many risk response types are available for a negative risk event in the pr
The correct answer is C. Four. The PMBOK Guide defines exactly four response strategies for negative risks: Avoid, Transfer, Mitigate, and Accept.
Question
You work as a project manager for BlueWell Inc. You are preparing to plan risk responses for your project with your team. How many risk response types are available for a negative risk event in the project?
Options
- ASeven
- BThree
- CFour
- DOne
How the community answered
(29 responses)- A3% (1)
- C90% (26)
- D7% (2)
Why each option
The PMBOK Guide defines exactly four response strategies for negative risks: Avoid, Transfer, Mitigate, and Accept.
Seven is incorrect; while PMBOK defines seven total risk responses combining both negative and positive strategies, only four apply specifically to negative risks.
Three is incorrect; some older frameworks listed three responses, but the current PMBOK standard clearly defines four distinct strategies for addressing negative risks.
PMBOK identifies four distinct strategies for negative risk events: Avoid (eliminate the threat by changing the plan), Transfer (shift impact to a third party), Mitigate (reduce probability or impact), and Accept (acknowledge without proactive action). Each addresses threats differently based on risk priority and feasibility.
One is incorrect; a single response type could not adequately address the variety of negative risk scenarios encountered across different project contexts.
Concept tested: Four negative risk response strategies - PMBOK
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.