You are the project manager for your organization. You are working with your project team to complete the qualitative risk analysis process. The first tool and technique you are using requires that yo
The correct answer is C. Impact. The primary tool and technique in the Perform Qualitative Risk Analysis process is the Probability and Impact Assessment. For each identified risk, the project team evaluates two dimensions: the likelihood (probability) that the risk will occur, and the Impact (consequence/effect
Question
You are the project manager for your organization. You are working with your project team to complete the qualitative risk analysis process. The first tool and technique you are using requires that you assess the probability and what other characteristic of each identified risk in the project?
Options
- ARisk owner
- BRisk category
- CImpact
- DCost
How the community answered
(26 responses)- A4% (1)
- B4% (1)
- C92% (24)
Explanation
The primary tool and technique in the Perform Qualitative Risk Analysis process is the Probability and Impact Assessment. For each identified risk, the project team evaluates two dimensions: the likelihood (probability) that the risk will occur, and the Impact (consequence/effect) on project objectives such as scope, schedule, cost, or quality if it does occur. These two dimensions are then used together - often in a Probability and Impact Matrix - to prioritize risks. Options A (Risk Owner), B (Risk Category), and D (Cost) are not the paired characteristic in this foundational assessment tool.