CAP · Question #366
CAP Question #366: Real Exam Question with Answer & Explanation
Sign in or unlock CAP to reveal the answer and full explanation for question #366. The question stem and answer options stay visible for context.
Security and Privacy Governance, Risk Management, and Compliance Program
Question
You are the project manager for your organization. You are working with your project team to complete the qualitative risk analysis process. The first tool and technique you are using requires that you assess the probability and what other characteristic of each identified risk in the project?
Options
- ARisk owner
- BRisk category
- CImpact
- DCost
Unlock CAP to see the answer
You've previewed enough free CAP questions. Unlock CAP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Management#Qualitative Risk Analysis#Probability and Impact#Risk Assessment