CAP · Question #365

Kelly is the project manager of the BHH project for her organization. She is completing the risk identification process for this portion of her project. Which one of the following is the only thing th

The correct answer is D. Risk register. According to the PMBOK Guide, the sole output of the Identify Risks process is the Risk Register. The Risk Register is created fresh during this process and contains the list of identified risks, potential risk owners, and potential risk responses. Option B (Risk Register Updates

Security and Privacy Governance, Risk Management, and Compliance Program

Question

Kelly is the project manager of the BHH project for her organization. She is completing the risk identification process for this portion of her project. Which one of the following is the only thing that the risk identification process will create for Kelly?

Options

  • AProject document updates
  • BRisk register updates
  • CChange requests
  • DRisk register

How the community answered

(21 responses)
  • B
    5% (1)
  • C
    10% (2)
  • D
    86% (18)

Explanation

According to the PMBOK Guide, the sole output of the Identify Risks process is the Risk Register. The Risk Register is created fresh during this process and contains the list of identified risks, potential risk owners, and potential risk responses. Option B (Risk Register Updates) is incorrect because at this stage the register is being created, not updated - updates occur in subsequent risk management processes. Options A (project document updates) and C (change requests) are outputs of other processes, not Identify Risks.

Topics

#Risk identification#Risk register#Project management#Risk management process