CAP · Question #342
Which of the following statements are true about security risks? Each correct answer represents a complete solution. Choose three.
The correct answer is B. They can be analyzed and measured by the risk analysis process. C. They can be mitigated by reviewing and taking responsible actions based on possible risks. D. They are considered an indicator of threats coupled with vulnerability.. B is correct: Risk analysis processes exist specifically to analyze and measure security risks, assessing likelihood and potential impact. C is correct: Risks can be mitigated-reduced to an acceptable level-through review and responsible action; mitigation is a core risk response
Question
Which of the following statements are true about security risks? Each correct answer represents a complete solution. Choose three.
Options
- AThey can be removed completely by taking proper actions.
- BThey can be analyzed and measured by the risk analysis process.
- CThey can be mitigated by reviewing and taking responsible actions based on possible risks.
- DThey are considered an indicator of threats coupled with vulnerability.
How the community answered
(26 responses)- A12% (3)
- B88% (23)
Explanation
B is correct: Risk analysis processes exist specifically to analyze and measure security risks, assessing likelihood and potential impact. C is correct: Risks can be mitigated-reduced to an acceptable level-through review and responsible action; mitigation is a core risk response strategy. D is correct: In security, risk is defined as the combination of a threat (an actor or event that could cause harm) and a vulnerability (a weakness that can be exploited), making it an indicator of threats coupled with vulnerability. A is incorrect because security risks can never be completely eliminated; residual risk always remains. Proper controls reduce risk to an acceptable level, but complete removal is not achievable.