CAP · Question #341
Mark is the project manager of the BFL project for his organization. He and the project team are creating a probability and impact matrix using RAG rating. There is some confusion and disagreement…
The correct answer is D. Look-up table. In a probability and impact matrix using RAG (Red, Amber, Green) rating, the actual priority level assigned to a specific combination of probability and impact is determined by a look-up table. This table maps each intersection of probability score and impact score to a…
Question
Mark is the project manager of the BFL project for his organization. He and the project team are creating a probability and impact matrix using RAG rating. There is some confusion and disagreement among the project team as to how a certain risk is important and priority for attention should be managed. Where can Mark determine the priority of a risk given its probability and impact?
Options
- ARisk response plan
- BProject sponsor
- CRisk management plan
- DLook-up table
How the community answered
(26 responses)- A4% (1)
- B12% (3)
- C8% (2)
- D77% (20)
Explanation
In a probability and impact matrix using RAG (Red, Amber, Green) rating, the actual priority level assigned to a specific combination of probability and impact is determined by a look-up table. This table maps each intersection of probability score and impact score to a priority rating (e.g., High/Red, Medium/Amber, Low/Green). The Risk Management Plan defines the methodology and thresholds used to build that matrix, but when a team member needs to resolve confusion about where a specific risk falls, they consult the look-up table embedded in or accompanying the matrix. The Risk Response Plan is created after prioritization, and the project sponsor is a stakeholder, not a reference document.
Topics
Community Discussion
No community discussion yet for this question.