Which of the following components ensures that risks are examined for all new proposed change requests in the change control system?

The correct answer is D. Integrated change control. Integrated change control is the process that reviews all proposed change requests across all project knowledge areas, ensuring that risks are examined for every change before approval.

Security and Privacy Governance, Risk Management, and Compliance Program

Question

Which of the following components ensures that risks are examined for all new proposed change requests in the change control system?

Options

  • ARisk monitoring and control
  • BScope change control
  • CConfiguration management
  • DIntegrated change control

How the community answered

(29 responses)
  • A
    3% (1)
  • B
    7% (2)
  • C
    3% (1)
  • D
    86% (25)

Why each option

Integrated change control is the process that reviews all proposed change requests across all project knowledge areas, ensuring that risks are examined for every change before approval.

ARisk monitoring and control

Risk monitoring and control tracks and responds to previously identified risks and monitors risk triggers throughout the project but does not govern the review process for new change requests.

BScope change control

Scope change control manages changes to the project scope boundary but is a subset of integrated change control and does not ensure risk examination across all types of change requests.

CConfiguration management

Configuration management controls changes to product specifications and project artifacts but does not specifically ensure that risk is evaluated for all proposed change requests across the project.

DIntegrated change controlCorrect

Integrated change control is the process responsible for reviewing all change requests and evaluating their impact across the entire project management plan, including their risk implications, before a change is approved or rejected. By centralizing the review of all proposed changes, it ensures that no change is made without a cross-cutting assessment of risk, schedule, cost, and scope impacts. This holistic, integrated approach is specifically designed to ensure consistent risk examination for all new change requests within the change control system.

Concept tested: Integrated change control ensuring risk review of change requests

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Integrated Change Control#Change Management#Risk Management#System Lifecycle