nerdexam
(ISC)2

CAP · Question #319

You work as the project manager for Bluewell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decide, with your stakeholders' approval, to fast…

The correct answer is B. Risks. Fast tracking a project compresses the schedule by performing activities in parallel that were originally sequential, which inherently increases project risk due to overlapping dependencies.

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You work as the project manager for Bluewell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decide, with your stakeholders' approval, to fast track the project work to get the project done faster. When you fast track the project, what is likely to increase?

Options

  • AHuman resource needs
  • BRisks
  • CCosts
  • DQuality control concerns

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    94% (29)
  • C
    3% (1)

Why each option

Fast tracking a project compresses the schedule by performing activities in parallel that were originally sequential, which inherently increases project risk due to overlapping dependencies.

AHuman resource needs

Fast tracking reorganizes the timing of existing work rather than adding new work, so it does not inherently increase human resource needs.

BRisksCorrect

Fast tracking overlaps activities that were planned to execute sequentially, creating situations where later tasks begin before upstream tasks are fully complete, which increases the probability of rework if earlier deliverables require changes. The compressed sequencing removes buffer time for identifying and correcting errors before dependent work begins, directly elevating overall project risk. Unlike crashing, fast tracking does not necessarily add cost, but it does consistently and predictably increase risk as the primary consequence.

CCosts

Increased costs are a typical consequence of crashing - adding resources to compress the schedule - not of fast tracking, which achieves schedule compression by parallelizing existing activities.

DQuality control concerns

While quality issues can arise indirectly from fast tracking, increased risk is the primary, most direct, and most universally cited consequence of overlapping previously sequential activities.

Concept tested: Fast tracking schedule compression and its impact on risk

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Project Risk Management#Schedule Compression#Fast Tracking

Community Discussion

No community discussion yet for this question.

Full CAP Practice