CAP · Question #311

You are the project manager of the HJK Project for your organization. You and the project team have created risk responses for many of the risk events in the project. Where should you document the…

The correct answer is C. Risk register. The risk register is the central repository for all identified risks, their proposed responses, owners, and current status throughout the project. It is continuously updated as the project progresses.

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You are the project manager of the HJK Project for your organization. You and the project team have created risk responses for many of the risk events in the project. Where should you document the proposed responses and the current status of all identified risks?

Options

  • ARisk management plan
  • BStakeholder management strategy
  • CRisk register
  • DLessons learned documentation

How the community answered

(49 responses)
  • A
    2% (1)
  • C
    94% (46)
  • D
    4% (2)

Why each option

The risk register is the central repository for all identified risks, their proposed responses, owners, and current status throughout the project. It is continuously updated as the project progresses.

ARisk management plan

The risk management plan describes the methodology, roles, and processes for managing risks but does not record individual risk events or track their response status.

BStakeholder management strategy

The stakeholder management strategy focuses on approaches for engaging and communicating with stakeholders, not on documenting or tracking identified project risks.

CRisk registerCorrect

The risk register documents every identified risk event, its probability and impact assessment, proposed risk responses, risk owners, and current status. It serves as the living project document that tracks each risk from identification through closure. It is updated iteratively as risk responses are planned and implemented, making it the definitive source of record for all risk-related information.

DLessons learned documentation

Lessons learned documentation captures knowledge and insights at project or phase completion, not the real-time tracking of risk events and their proposed responses.

Concept tested: Risk register as the risk documentation repository

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Risk Management#Risk Register#Project Documentation#Risk Response Planning