nerdexam
(ISC)2

CAP · Question #310

Beth is the project manager of the BFG Project for her company. In this project Beth has decided to create a contingency response based on the performance of the project schedule. If the project…

The correct answer is A. SV=EV-PV. In Earned Value Management (EVM), Schedule Variance (SV) measures whether a project is ahead of or behind schedule in terms of value. The correct formula is SV = EV - PV (Earned Value minus Planned Value). A positive SV means ahead of schedule; negative means behind. Option B…

Security and Privacy Governance, Risk Management, and Compliance Program

Question

Beth is the project manager of the BFG Project for her company. In this project Beth has decided to create a contingency response based on the performance of the project schedule. If the project schedule variance is greater than $10,000 the contingency plan will be implemented. What is the formula for the schedule variance?

Options

  • ASV=EV-PV
  • BSV=EV/AC
  • CSV=PV-EV
  • DSV=EV/PV

How the community answered

(36 responses)
  • A
    89% (32)
  • B
    3% (1)
  • C
    3% (1)
  • D
    6% (2)

Explanation

In Earned Value Management (EVM), Schedule Variance (SV) measures whether a project is ahead of or behind schedule in terms of value. The correct formula is SV = EV - PV (Earned Value minus Planned Value). A positive SV means ahead of schedule; negative means behind. Option B (EV/AC) is the Cost Performance Index (CPI). Option C (PV - EV) reverses the formula, producing inverse results. Option D (EV/PV) is the Schedule Performance Index (SPI), a ratio rather than a variance. The question's context about Beth's $10,000 threshold is a variance (difference), confirming SV = EV - PV is correct.

Topics

#Schedule Variance (SV)#Earned Value Management (EVM)#Project Schedule#Contingency Planning

Community Discussion

No community discussion yet for this question.

Full CAP Practice