Which of the following is not a part of Identify Risks process?
The correct answer is C. Decision tree diagram. The Identify Risks process in the PMBOK uses several diagramming techniques as tools and techniques, including: System or process flow charts (A), Influence diagrams (B), and Cause and effect diagrams (D) - also known as Ishikawa or fishbone diagrams. A Decision tree diagram (C)
Question
Which of the following is not a part of Identify Risks process?
Options
- ASystem or process flow chart
- BInfluence diagram
- CDecision tree diagram
- DCause and effect diagram
How the community answered
(35 responses)- A3% (1)
- B9% (3)
- C86% (30)
- D3% (1)
Explanation
The Identify Risks process in the PMBOK uses several diagramming techniques as tools and techniques, including: System or process flow charts (A), Influence diagrams (B), and Cause and effect diagrams (D) - also known as Ishikawa or fishbone diagrams. A Decision tree diagram (C) is NOT used in the Identify Risks process. Decision tree diagrams are used in the Perform Quantitative Risk Analysis process to model decision scenarios and calculate expected monetary values (EMV). This makes C the correct answer as the 'odd one out.'