In which of the following phases does the SSAA maintenance take place?
The correct answer is D. Phase 4. The DITSCAP (Defense Information Technology Security Certification and Accreditation Process) consists of four phases: Phase 1 - Definition, Phase 2 - Verification, Phase 3 - Validation, and Phase 4 - Post Accreditation. The System Security Authorization Agreement (SSAA) maintena
Question
In which of the following phases does the SSAA maintenance take place?
Options
- APhase 3
- BPhase 2
- CPhase 1
- DPhase 4
How the community answered
(24 responses)- A4% (1)
- B4% (1)
- D92% (22)
Explanation
The DITSCAP (Defense Information Technology Security Certification and Accreditation Process) consists of four phases: Phase 1 - Definition, Phase 2 - Verification, Phase 3 - Validation, and Phase 4 - Post Accreditation. The System Security Authorization Agreement (SSAA) maintenance takes place in Phase 4 (Post Accreditation). During this phase, the system is in operation and the SSAA is maintained and updated to reflect any changes to the system's security posture, ensuring ongoing accreditation compliance.
Topics
Community Discussion
No community discussion yet for this question.