(ISC)2(ISC)2
CAP · Question #288
CAP Question #288: Real Exam Question with Answer & Explanation
The correct answer is C: Stakeholder register. See the full explanation below for the reasoning.
Security and Privacy Governance, Risk Management, and Compliance Program
Question
You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. You will need all of the following as inputs to the qualitative risk analysis process except for which one?
Options
- ARisk management plan
- BRisk register
- CStakeholder register
- DProject scope statement
Topics
#Risk Management#Qualitative Risk Analysis#Project Management Process#Inputs
Community Discussion
No community discussion yet for this question.