nerdexam
(ISC)2

CAP · Question #288

You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. You will need all of the following as inputs to the qualit

The correct answer is C. Stakeholder register. The stakeholder register is not an input to qualitative risk analysis; it belongs to stakeholder management processes, not risk assessment processes.

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. You will need all of the following as inputs to the qualitative risk analysis process except for which one?

Options

  • ARisk management plan
  • BRisk register
  • CStakeholder register
  • DProject scope statement

How the community answered

(45 responses)
  • A
    4% (2)
  • C
    93% (42)
  • D
    2% (1)

Why each option

The stakeholder register is not an input to qualitative risk analysis; it belongs to stakeholder management processes, not risk assessment processes.

ARisk management plan

The risk management plan is a primary input because it defines the methodology, roles, risk categories, and thresholds used during qualitative analysis.

BRisk register

The risk register contains the list of identified risks that are assessed and prioritized during qualitative risk analysis.

CStakeholder registerCorrect

Per the PMBOK Guide, inputs to qualitative risk analysis include the risk management plan, project scope statement, risk register, enterprise environmental factors, and organizational process assets. The stakeholder register is used in stakeholder identification and engagement processes and is not required to prioritize risks by probability and impact.

DProject scope statement

The project scope statement provides context about project boundaries and deliverables, which helps evaluate the potential impact of each identified risk.

Concept tested: Qualitative risk analysis inputs per PMBOK Guide

Source: https://www.pmi.org/learning/library/qualitative-risk-analysis-process-pmbok-guide-9689

Topics

#Risk Management#Qualitative Risk Analysis#Project Management Process#Inputs

Community Discussion

No community discussion yet for this question.

Full CAP Practice