Thomas is a key stakeholder in your project. Thomas has requested several changes to the project scope for the project you are managing. Upon review of the proposed changes, you have discovered that…
The correct answer is D. Integrated change control. Integrated Change Control (D) is the formal process through which all change requests are reviewed, evaluated, and either approved or denied. It is the component that formally communicates the disposition of any proposed change request to stakeholders and the change control…
Question
Thomas is a key stakeholder in your project. Thomas has requested several changes to the project scope for the project you are managing. Upon review of the proposed changes, you have discovered that these new requirements are laden with risks and you recommend to the change control board that the changes be excluded from the project scope. The change control board agrees with you. What component of the change control system communicates the approval or denial of a proposed change request?
Options
- AConfiguration management system
- BChange log
- CScope change control system
- DIntegrated change control
How the community answered
(38 responses)- A8% (3)
- B3% (1)
- C3% (1)
- D87% (33)
Explanation
Integrated Change Control (D) is the formal process through which all change requests are reviewed, evaluated, and either approved or denied. It is the component that formally communicates the disposition of any proposed change request to stakeholders and the change control board. The Configuration Management System tracks versions and product baselines; the Change Log records all changes but does not approve/deny them; and the Scope Change Control System is a subset - only Integrated Change Control covers the full approval/denial communication across all knowledge areas.