CAP · Question #271
You are the project manager of the NHH project for your company. You have completed the first round of risk management planning and have created four outputs of the risk response planning process…
The correct answer is D. Organizational process assets updates. According to the PMBOK Guide, the outputs of the Plan Risk Responses process are: (1) Risk register updates, (2) Project management plan updates, (3) Project document updates, and (4) Risk-related contractual agreements (contracts). 'Organizational process assets updates' is…
Question
You are the project manager of the NHH project for your company. You have completed the first round of risk management planning and have created four outputs of the risk response planning process. Which one of the following is NOT an output of the risk response planning?
Options
- ARisk-related contract decisions
- BProject document updates
- CRisk register updates
- DOrganizational process assets updates
How the community answered
(47 responses)- A4% (2)
- B2% (1)
- C6% (3)
- D87% (41)
Explanation
According to the PMBOK Guide, the outputs of the Plan Risk Responses process are: (1) Risk register updates, (2) Project management plan updates, (3) Project document updates, and (4) Risk-related contractual agreements (contracts). 'Organizational process assets updates' is NOT an output of risk response planning - it is typically an output of processes like Close Project or Phase. The other three options (A, B, C) are all legitimate outputs of the Plan Risk Responses process, making D the correct answer.
Topics
Community Discussion
No community discussion yet for this question.